Most small restaurants, cafés and cloud kitchens in Delhi NCR can go from signed lease to soft launch in about 90 days, if licences are filed in the first fortnight and the fit-out is planned before work starts. This checklist breaks those 90 days into weeks, with the vendor or licence you need at each step, who owns each task, and the clauses, snags and launch steps that usually decide whether you open on time.
Timelines vary by location, size and brand. A 20-seat café in a ready commercial unit moves faster than a 100-cover dine-in that needs structural work, fire approvals or a liquor licence.
Before day 1: the groundwork
Do this before you start the 90-day clock:
- Concept: cuisine, format (dine-in, café, QSR, cloud kitchen), average bill and target customer
- Budget: a realistic setup budget plus three months of working capital
- Location shortlist: 3–5 options visited at lunch, evening and weekend
- Space checks: commercial use permitted, electrical load, water, drainage and an exhaust route
- Gas check: whether the building has a PNG line or can get one, or whether you will run on commercial LPG
- Alcohol decision: if you want a bar, check excise eligibility for that property before you commit
If you need cost benchmarks, read cost to open a café in Delhi NCR or cost to open a cloud kitchen in Delhi.
Site visit checklist before you sign
Take your chef or kitchen equipment vendor to the final one or two shortlisted spaces. Check:
- Sanctioned electrical load and how much more the discom can add
- Where the exhaust duct will exit, and whether neighbours or the society can object
- Floor drain points and slope; whether a grease trap can be fitted
- Water supply and storage
- Ceiling height for ducts and a false ceiling
- Fire exits and staircase width if you plan more than 50 seats
- Parking and delivery-rider waiting space
- Whether the previous tenant left exhaust, drainage or gas lines you can reuse
Weeks 1–2: lock the location and start paperwork
Goal: sign the space and file the first registrations.
- Negotiate rent, deposit, lock-in and a rent-free fit-out period (30–60 days is a common ask)
- Get the landlord NOC and property documents you will need for licences
- Sign and register the rent agreement
- Choose your business structure (proprietorship, partnership, LLP or company)
- Open a current account
- Apply for GST registration (no government fee; published guides say 3–7 days)
- Apply for FSSAI registration or state licence on FoSCoS
Per the FoSCoS list updated 1 April 2026, restaurants with turnover up to ₹1.5 crore need registration at ₹100 a year, and those between ₹1.5 crore and ₹50 crore need a state licence at ₹5,000 a year. Published processing times range from about 7 days to 60 days. The FSSAI licence cost and process guide walks through the application, and the GST guide for restaurants explains which tax rate applies to your format.
Vendors to bring in: FSSAI licence agents, CA and accounting firms, and, if you want one partner to manage the whole project, restaurant setup consultants.
Lease clauses to insist on
Your lease shapes the whole 90 days. Before you sign, ask for:
- Rent-free fit-out period in writing, with a start date tied to handover of the keys, not the signing date
- Permission for alterations: exhaust openings, drainage changes, signage and load increase
- Landlord NOC and copies of ownership documents for licence applications
- Lock-in period you can live with if the outlet underperforms
- Clarity on who pays for load enhancement, water and common-area charges
- Reinstatement terms at exit, so you know what you must remove
Weeks 2–3: design and layout
Goal: freeze the layout before anyone breaks a wall.
- Brief 2–3 interior designers with your concept, budget and seat count
- Get a kitchen layout from your chef and equipment vendor at the same time
- Decide seat count with fire rules in mind (Delhi fire officials cite 50 seats as the NOC threshold under the National Building Code)
- Plan electrical load, plumbing points, drainage and grease trap
- Plan exhaust route and fresh air
- Finalise the design and a bill of quantities (BOQ)
Kitchen and dining design must be done together. Many delays come from equipment that does not fit, or exhaust that was not planned into the ceiling. The commercial kitchen equipment checklist and the kitchen exhaust and ducting guide help you brief vendors properly.
Vendors: restaurant interior designers, commercial kitchen equipment suppliers, kitchen exhaust and ducting contractors. See restaurant interior and fit-out cost per sq ft to compare quotes.
Weeks 3–4: contracts and orders
Goal: sign vendors with clear scope, timelines and payment milestones.
- Sign the fit-out contract with a timeline and penalty clause
- Place the kitchen equipment order (lead times can be 2–6 weeks for fabricated items)
- Order exhaust hood and ducting
- Apply for gas: commercial LPG through a distributor or PNG through IGL
- Apply for any additional electrical load
- Register under the Shop and Establishment law for your state
- Start the health trade licence application with your local body
In June 2025 Delhi removed the Delhi Police licence requirement for eating houses and moved licensing to local bodies, so check your local body's current process rather than older checklists. The same month, MCD launched a web portal that issues health trade licences once documents are uploaded and the fee is paid.
On gas: an April 2026 Delhi directive said businesses in areas with a PNG network would get commercial LPG only if they had a PNG connection or had applied for one. IGL has also been pushing commercial PNG connections across Delhi NCR in 2026. If your building is on the network, file the PNG application early, because pipeline work inside commercial buildings can need permissions from the landlord or society.
Vendors: gas pipeline installers. Read LPG vs PNG for commercial kitchens before you choose.
How to compare quotes in week 3
Ask every vendor in a category for a quote against the same brief. A simple comparison sheet keeps it honest:
| Line to compare | Vendor A | Vendor B | Vendor C |
|---|---|---|---|
| Scope covered (attach BOQ) | |||
| Items excluded | |||
| Brands and material specs | |||
| Total before GST | |||
| GST treatment and invoice | |||
| Start and completion dates | |||
| Payment milestones | |||
| Warranty and AMC terms | |||
| Past restaurant projects visited | |||
| Delay penalty accepted? |
If one quote is far cheaper, check the exclusions row first. Missing ducting, electrical points or installation charges are the usual reasons.
Contract clauses to insist on
For the fit-out, kitchen equipment, exhaust and gas contracts, put these in writing:
- Detailed scope and BOQ attached to the contract, with brands and specs
- Fixed start and completion dates, and a delay penalty per week
- Milestone payments tied to visible work, not calendar dates
- Retention: hold back a small share of each bill until snags are closed. Public-sector interior tenders in India commonly retain up to 5% of contract value through a 12-month defect liability period; private contracts vary, so negotiate your own figure
- Change-order process: any change in scope or price must be approved in writing before work starts
- Warranty on waterproofing, electrical, joinery and equipment, with a named period
- Testing and handover: gas pressure test, electrical test and equipment trial run before final payment
- Site cleaning and debris removal included in scope
Weeks 5–8: fit-out in progress
Goal: civil, electrical and plumbing work done; services installed.
- Civil work, flooring, false ceiling
- Electrical wiring, DB, lighting points
- Plumbing, drainage, grease trap
- Exhaust ducting and fresh-air installation
- Gas pipeline installation and pressure testing
- Fire safety: extinguishers, detectors, signage and, where required, sprinklers and alarm
- CCTV and network cabling
- Apply for fire NOC if your seating or area requires it (published guides give 15–60 days)
- Hire your head chef or kitchen lead
Visit the site at least twice a week. Small changes are cheap on paper and expensive once tiles are laid.
Week-by-week inside the fit-out
| Week | Typical work on site | What you check |
|---|---|---|
| 5 | Demolition, civil work, plumbing and drainage lines | Floor slopes to drains, grease trap position |
| 6 | Electrical conduits, AC and exhaust duct routes, ceiling framing | Duct route clears beams, power points match equipment list |
| 7 | Ceiling closed, flooring, wall finishes start; gas line laid | Anti-skid kitchen floor, gas line route and valves |
| 8 | Joinery, lighting, fire safety fittings, CCTV | Counter heights, lighting levels, extinguisher positions |
Take dated photos of pipes, conduits and drains before the ceiling and floor close. They save hours when something leaks later.
Vendors: fire safety and CCTV installers. See fire NOC for restaurants in Delhi and the full restaurant licences list for Delhi.
Need vendors for this stage? Post your fit-out requirement and get calls from up to 3 rated interior firms.
Weeks 7–9: menu, brand and systems
Goal: everything a customer sees and every system staff will use.
- Finalise menu, recipes, portion sizes and food cost
- Test recipes with your chef and price the menu
- Finalise brand name, logo, signage and menu design
- Select POS, set up menu, taxes, printers and KOT flow
- Select raw material suppliers and agree credit terms
- Choose packaging for takeaway and delivery and test it
- Order uniforms
Write standard recipes with weights, not just ingredient lists. They are what let a second cook produce the same dish on day 30 as the chef did on day 1.
Vendors: branding and menu design studios, POS and billing software, raw material suppliers, food packaging suppliers, uniform makers. Helpful reads: how to choose a restaurant POS in India and the food packaging guide for delivery.
Weeks 9–10: equipment, furniture and hiring
Goal: the space is ready to cook in.
- Equipment delivery, installation and trial run
- Furniture delivery and placement
- Check every burner, fridge, freezer and exhaust fan under load
- Hire the rest of the team: cooks, helpers, servers, baristas, cashier
- Book an AMC for critical equipment
- Book pest control before food is stored on site
Pest control records are part of good food safety practice and inspection readiness. See pest control for restaurants and FSSAI.
Vendors: restaurant furniture makers, staff and chef placement agencies, commercial pest control, kitchen repair and AMC. For pay benchmarks, read restaurant staff salaries in Delhi.
Weeks 10–11: online presence and aggregators
Goal: customers can find you before you open.
- Food photography for menu and social media
- Apply on Swiggy and Zomato partner portals (FSSAI, GST, PAN, bank details, menu)
- Create or claim your Google Business Profile
- Set up Instagram and post the build-up
- Plan launch offers and a first-month marketing budget
Aggregator listings need verification, so do not leave them to the last week. One 2026 onboarding guide estimates 3–7 working days from complete documents to going live, if nothing is flagged; mismatched names or addresses across FSSAI, GST and bank records are a common cause of rejection. Read how to list your restaurant on Swiggy and Zomato and food photography for Swiggy and Zomato. If you plan to hire outside help for launch marketing, the restaurant marketing agency guide explains what to ask.
Vendors: food photographers, social media managers, Swiggy and Zomato consultants.
Week 12: deep clean, snags, training and dry runs
Goal: the team can run a full service without you stepping in.
- Post-construction deep cleaning of kitchen and dining
- Walk the site with every contractor and close the snag list
- Staff training: recipes, plating, hygiene, service steps, POS
- Two or three dry runs cooking the full menu
- Check all licences are in hand or applied, and display them where required
- Stock opening inventory
Vendors: deep cleaning services.
Snag list for the final walk-through
Walk the space with your designer, equipment vendor and electrician. Log each issue with a photo, owner and deadline.
Kitchen
- Every burner lights evenly; gas valves and leak test done
- Exhaust pulls smoke at full cooking load; no back-draft into dining
- Fridges and freezers hold temperature overnight
- Floor drains clear fast; no standing water near the line
- Grease trap accessible for cleaning
- Wall and floor joints sealed (pest entry points closed)
- Sinks, taps and hot water working
Dining and front
- No loose tiles, chipped edges or wobbling tables
- Lighting levels right at night, all fixtures working
- AC cools the full room at peak occupancy
- Washroom fittings, flush and exhaust working
- Signage lit; main door and glass sound and secure
Systems and safety
- POS prints KOTs to the right stations; UPI and card payments tested
- CCTV recording and viewable on your phone
- Extinguishers mounted and charged; exit signs lit; exits clear
- Wi-Fi working for staff devices and aggregator tablets
Release the final payment, or the retention, only once snags are closed.
Week 13: soft launch
Goal: open quietly, fix fast, then launch publicly.
- Soft launch for 3–5 days with invited guests, friends and neighbours
- Collect feedback on taste, portion, speed and service
- Fix menu items, timings and staff roles
- Switch on delivery apps once kitchen timings are stable
- Public launch with your planned marketing push
Expect problems in the first two weeks. That is what the soft launch is for.
Soft-launch playbook, day by day
| Day | Focus | What to do |
|---|---|---|
| 1 | Friends and family, limited menu | Run one service; time every ticket from KOT to pass |
| 2 | Neighbours and local businesses | Add the next set of dishes; test takeaway packing |
| 3 | Invited guests at full seating | Run a full rush; check POS, billing and table turns |
| 4 | Fix day | Change recipes, prep lists and staff roles based on notes |
| 5 | Delivery test | Switch on aggregators in a limited window; check packaging on arrival |
Keep a simple feedback card on each table with three questions: taste, speed and whether they would come back. Hold a 15-minute team huddle after every service and write down the three biggest problems.
Who does what
A clear split of roles saves weeks of back-and-forth.
| Role | Main responsibilities |
|---|---|
| Owner | Concept, budget, lease, final approvals, hiring key staff, payments |
| Head chef / kitchen lead | Menu, recipes, kitchen layout input, equipment list, kitchen training |
| Interior designer or turnkey firm | Layout, drawings, BOQ, site execution or supervision |
| Kitchen equipment vendor | Kitchen layout, fabrication, installation, trial run |
| Licence agent or CA | FSSAI, GST, Shop and Establishment, trade licence, accounts setup |
| Setup consultant (optional) | Overall project plan, vendor coordination, launch readiness |
Owner vs vendor responsibility by task
| Task | Owner | Vendor or partner |
|---|---|---|
| Lease, landlord NOC, property papers | Leads and signs | Lawyer or CA reviews |
| FSSAI, GST, shop registration | Supplies documents, signs | Licence agent or CA files and follows up |
| Kitchen layout | Approves | Chef and equipment vendor draw it |
| Exhaust and fresh air | Approves route with landlord | Ducting contractor designs and installs |
| Gas connection | Applies, pays deposit | Installer lays line and pressure tests |
| Fire safety and NOC | Decides seat count | Fire safety vendor installs; consultant files if needed |
| Menu and costing | Final call on price | Chef develops recipes and costs |
| Aggregator listing | Owns the account and bank details | Photographer, listing consultant support |
| Snag closure | Signs off | Each contractor fixes their own items |
If you are running the project yourself, hold a short weekly meeting with your designer, equipment vendor and chef. Most clashes, such as a duct running where a beam is, are caught early this way.
Worked examples: QSR vs café vs fine dine
These are planning illustrations built from the ranges in this guide, not promises. Your site and approvals decide the real dates.
| Milestone | QSR in an ex-restaurant unit | 40-seat café in a warm shell | 120-cover fine dine in a bare shell |
|---|---|---|---|
| Design freeze | Week 2 | Week 3 | Weeks 4–5 |
| Fit-out duration | 4–6 weeks | 6–8 weeks | 10–16 weeks |
| Fire NOC | Usually not, if under thresholds | Usually not, if under 50 seats | Likely needed; allow 15–60 days |
| Key long-lead item | Signage and counter | Coffee machine and bar counter | Custom furniture, HVAC, exhaust |
| Soft launch | Around week 9–10 | Around week 12–13 | Often month 5–6 |
QSR: speed comes from reusing exhaust, drainage and load. The risk is the old ducting; get it inspected and cleaned before you rely on it.
Café: the coffee machine, grinder and bar counter are the long-lead items. Order the machine early through coffee and beverage machine suppliers and design the bar around its size and water line.
Fine dine: more seats push you into fire NOC territory, and custom furniture and HVAC take longer. If you plan a bar, the excise process often sets the opening date, not the fit-out.
Budget checkpoints along the timeline
Cash goes out in waves. Plan for these approximate points:
| Week | Typical payments |
|---|---|
| 1–2 | Security deposit, first rent, agreement registration, licence fees and agent fees |
| 3–4 | Advances to interior contractor, kitchen equipment vendor and exhaust fabricator |
| 5–8 | Stage payments for fit-out, gas pipeline, fire safety items |
| 9–10 | Balance for equipment, furniture, POS hardware, uniforms, branding |
| 11–12 | Photography, opening inventory, packaging, staff salaries for training weeks |
| 13 | Launch marketing, first full month of salaries and rent |
Keep at least three months of running costs untouched by these payments. That reserve is what carries you through the first slow weeks.
Documents to keep ready
Licence applications and aggregator onboarding ask for many of the same documents. Keep scanned copies in one folder:
- PAN and Aadhaar of owners or partners
- Business registration (partnership deed, LLP or company documents) if applicable
- Rent agreement and landlord NOC
- Property ownership proof or electricity bill of the premises
- Layout plan of the premises, with seating marked
- Passport-size photographs
- Cancelled cheque or bank statement of the business account
- List of food categories and menu
- Water test report, if your local body or FSSAI category asks for it
Use exactly the same business name and address spelling on every application. Small differences between FSSAI, GST and bank records slow down aggregator verification.
Licences at a glance
| Licence or registration | When to start | Published time range | Fee / where to check |
|---|---|---|---|
| GST registration | Week 1 | 3–7 days | No government fee; gst.gov.in |
| FSSAI registration / state licence | Week 1 | About 7–60 days | ₹100 or ₹5,000 a year; foscos.fssai.gov.in |
| Shop and Establishment | Weeks 3–4 | 1–15 days | State labour department |
| Health trade licence | Weeks 3–4 | 1–8 weeks | MCD / NDMC / local authority |
| Fire NOC (if required) | Weeks 5–8 | 15–60 days | Delhi Fire Service / state fire dept |
| Signage permission | Weeks 5–8 | Varies | Local body |
| Music licences (if playing recorded music) | Weeks 9–10 | Varies | IPRS / PPL |
| Liquor licence (if serving alcohol) | Before lease, if possible | Often months | State excise department |
Time ranges come from published industry guides and vary a lot in practice. If you plan to serve alcohol, check eligibility before you sign the lease, since location rules can rule a property out.
NCR notes: Delhi, Noida, Gurugram and beyond
The central steps, FSSAI and GST, are the same across NCR. Local steps differ:
- Delhi: shop registration under the Delhi Shops and Establishments Act is online through the labour department, which has described it as free, and periodic renewal was dropped in 2025. Health trade licences come from MCD's online portal or NDMC, depending on your area. FSSAI licence agents in Delhi handle these filings regularly.
- Gurugram and Faridabad: Haryana applies the Punjab Shops and Commercial Establishments Act, 1958, with online registration through state portals. Trade licences and fire approvals sit with the local municipal corporation and Haryana fire services. Mall units often come with their own fit-out rules and approval drawings; see restaurant interior firms in Gurgaon.
- Noida and Ghaziabad: Uttar Pradesh rules and the local development authority or municipal body apply. Many Noida sites are in commercial complexes with their own exhaust and gas rules, so ask the maintenance office early. Compare kitchen equipment suppliers in Noida and gas pipeline installers in Ghaziabad.
Portals and fees change often. Treat any list, including this one, as a starting point and confirm on the official site or with your agent.
Common mistakes and delays that push your opening back
- Signing a lease before checking permissions. Confirm commercial use, load and exhaust route first.
- Designing dining and kitchen separately. Equipment and exhaust must be in the design from day one.
- Filing licences late. Inspections need the site to be ready, and slots can take time.
- Changing the design mid-way. Every change adds days and money.
- No buffer. Keep two to three weeks spare, and a rent-free period to cover it.
- Load enhancement left late. Discom upgrades for extra electrical load can take weeks; apply as soon as the equipment list is known.
- Gas treated as an afterthought. A burner range is useless without a tested connection.
- Mismatched documents. Different spellings of the business name across registrations hold up aggregator onboarding.
- Hiring the team too late. Untrained staff on opening day cost more in bad reviews than two extra weeks of salary.
- Opening with the full menu. A long menu stretches prep, stock and a new team all at once.
Quick checklist
- Concept, budget and location shortlist ready before day 1
- Lease signed with rent-free period; GST and FSSAI filed in week 1
- Interior and kitchen layout frozen by week 3
- Fit-out, equipment, exhaust and gas orders placed by week 4
- Trade licence, Shop and Establishment, and fire NOC (if needed) filed during fit-out
- Menu, brand, POS, packaging and suppliers finalised by week 9
- Equipment installed and team hired by week 10
- Aggregator listings and Google profile live by week 11
- Deep clean, snag list closed, training and dry runs in week 12
- Soft launch in week 13
Want help at any step? Post your requirement and get calls from up to 3 rated setup consultants, or pick a specific category such as interiors or licence agents.
Sources
- FoSCoS – Kind of Business eligibility and fees (updated 01.04.2026)
- Restroworks – Licences needed for a restaurant
- Petpooja – Indian restaurant licences
- Petpooja – Café licence and FSSAI registration guide
- Gofrugal – 12 licences required to open a restaurant in India
- DineOpen – Restaurant licences in India
- India Briefing – Delhi's restaurant industry and licensing
- Outlook Traveller – Delhi scraps police permission for restaurants and hotels
- Tribune – No police NOC needed for health trade licences in Delhi
- Business Standard – How safe are Delhi eateries (fire NOC threshold)
- PNGRB – Commercial PNG FAQs
- The Week (PTI) – MCD rolls out web portal for instant health trade licence, June 2025
- NDMC – Online health licence system
- TaxGuru – Delhi Labour Commissioner notice on online shop registration
- Daily Pioneer – Delhi scraps mandatory renewal of shop registration (2025)
- Haryana Labour Department – Shops and Commercial Establishments
- Devdiscourse – Delhi introduces new rules for commercial LPG supply (April 2026)
- ThePrint – IGL's piped natural gas push in Delhi-NCR
- Agile Regulatory – Swiggy restaurant partner registration process in 2026
- Indian Bank – Interior furnishing work tender (retention and defect liability terms)
- Inspectly360 – Commercial kitchen snagging checklist